Arrow Diagramming Method |
|
Definition:
This method of constructing a project network diagram uses
arrows to represent the activities and connects them at nodes to
show their dependencies This technique is also called
activity-on-arrow (AOA) and, although less prevalent than PDM,
is still the technique of choice in some application areas. ADM
uses only finish-to-start dependencies and may require the use
of dummy activities to define all logical relationships
correctly. ADM can be done manually or on a computer. |
|
|